SR 826/Palmetto Expwy
Plus sign Construction Fri 05-26-2017 to Fri 06-02-2017

NIGHTTIME/DAYTIME LANE CLOSURES ON SR 826/PALMETTO EXPRESSWAY AND I-75:

 

Daytime Lane Closure: Friday, May 26, and from Tuesday, May 30 to Friday, June 2 from 10 a.m. to 3:30 p.m.

 

On I-75 one northbound inside lane and one southbound inside lane will be closed between SR 826/Palmetto Expressway and NW 138 Street.

 

Tuesday, May 30 to Thursday, June 1 from 11 p.m. to 5 a.m. of the following morning:

 

On SR 826/Palmetto Expressway northbound the ramp to I-75 northbound will be closed.

 

Northbound drivers on SR 826/Palmetto Expressway heading to I-75 northbound may:

 

·         Take the exit ramp to NW 154 Street

·         Turn west on NW 154 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the ramp to I-75 northbound

 

Tuesday, May 30 to Thursday, June 1, from 10 p.m. to 5 a.m. of the following morning:

 

On Okeechobee Road ALL southbound and northbound lanes will be closed at the SR 826/Palmetto Expressway bridge. 

 

Southbound drivers on Okeechobee Road may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 74 Street

·         Turn east on NW 74 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to Okeechobee Road

·         Turn south on Okeechobee Road

 

Northbound drivers on Okeechobee Road may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to NW 103 Street/West 49 Street

·         Turn west on NW 103 Street/West 49 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to Okeechobee Road

·         Turn west on Okeechobee Road

 

Southbound drivers on SR 826/Palmetto Expressway heading to Okeechobee Road southbound may:

 

·         Take the exit ramp to NW 74 Street

·         Turn east on NW 74 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to Okeechobee Road

·         Turn south on Okeechobee Road

 

Northbound drivers on SR 826/Palmetto Expressway heading to Okeechobee road northbound may:

 

·         Take the exit ramp on NW 103 Street/West 49 Street

·         Turn west on NW 103 Street/West 49 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to Okeechobee Road northbound

 

Southbound drivers on Okeechobee Road heading to SR 826/Palmetto Expressway northbound:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 74 Street

·         Turn east on NW 74 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

 

Tuesday, May 30 to Wednesday, May 31 from 11 p.m. to 5 a.m. of the following morning:

 

On SR 826/Palmetto Expressway southbound ALL lanes will be closed from the entrance ramp to I-75 northbound to NW 122 Street.

 

Southbound drivers on SR 826/Palmetto Expressway may:

 

  • Take the exit ramp to I-75 northbound
  • Take the exit ramp to Hialeah Gardens Boulevard
  • Turn south on Hialeah Gardens Boulevard
  • Turn east on NW 122 Street/West 68 Street
  • Take the entrance ramp to SR 826/Palmetto Expressway southbound

 

Tuesday, May 30 to Thursday, June 1, from 10 p.m. to 5 a.m. of the following morning:

 

On South River Drive ALL northbound and southbound lanes will be closed at SR 826/Palmetto Expressway.

 

Southbound drivers on South River Drive may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Turn east on NW 74 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to South River Drive

·         Turn south on South River Drive

 

Northbound drivers on South River Drive may:

 

·         Take the bridge over the canal to Okeechobee Road northbound

·         Take the southbound bridge over the canal on the west side of SR 826/Palmetto Expressway

·         Turn north on South River Drive

 

Tuesday, May 30 to Thursday, June 1 from 10 p.m. to 5 a.m. of the following morning;

 

On NW 122 Street/West 68 Street ALL eastbound lanes will be closed at the SR 826/Palmetto Expressway bridge.

 

Drivers heading eastbound on NW 122 Street/West 68 Street may:

 

  • Turn south on West 21 Ct.
  • Turn east on West 60 Street
  • Turn north on West 16 Avenue
  • Turn east or west on NW 122 Street/West 68 Street

 

Tuesday, May 30 to Thursday, June 1, from 10 p.m. to 5 a.m. of the following morning:

 

On NW 36 Street ALL eastbound and westbound lanes will be closed at the SR 826/Palmetto Expressway bridge.

 

Drivers heading westbound on NW 36 Street may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to NW 58 Street

·         Turn west on NW 58 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 36 Street and go west

 

Drivers heading eastbound on NW 36 Street may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 25 Street

·         Turn east on NW 25 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to NW 36 Street and go east

 

Westbound drivers on NW 36 Street heading to SR 826/Palmetto Expressway southbound may:

 

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to NW 58 Street

·         Turn west on NW 58 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

 

Eastbound drivers on NW 36 Street heading to SR 826/Palmetto Expressway northbound

 

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 25 Street

·         Turn east on NW 25 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

 

Northbound drivers on SR 826/Palmetto Expressway heading to NW 36 Street westbound may:

 

·         Take the exit ramp to NW 36 Street

·         Go east on NW 36 Street

·         Turn north on NW 72 Street

·         Turn west on NW 58 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway southbound

·         Take the exit ramp to NW 36 Street and go west

 

Southbound drivers on SR 826/Palmetto Expressway heading to NW 36 Street eastbound may:

 

·         Take the exit ramp to NW 36 Street

·         Go west on NW 36 Street

·         Turn south on NW 79 Street

·         Turn east on NW 25 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Take the exit ramp to NW 36 Street and go east

 

Tuesday, May 30 to Thursday, June 1 from 10 p.m. to 5 a.m. of the following morning:

 

On NW 74 Street ALL eastbound and westbound lanes will be closed at SR 826/Palmetto Expressway

 

Drivers heading eastbound on NW 74 Street may:

 

·         Turn south on NW 77 Ct.

·         Turn east on NW 58 Street

·         Take the entrance ramp to SR 826/Palmetto Expressway northbound

·         Exit on NW 74 Street

 

Drivers heading westbound on NW 74 Street may:

 

·         Turn south on NW 74 Avenue

·         Turn west on NW 58 Street

·         Turn north (right) on NW 79 Avenue and make an immediate right onto NW 77 Ct.

·         Continue on NW 77 Ct. to NW 74 Street

 

Tuesday, May 30 from 10 p.m. to 5 a.m. of the following morning:

 

On SR 826/Palmetto Expressway one northbound outside lane will be closed at Okeechobee Road.

 

Thursday, June 1 from 11 p.m. to 5 a.m. of the following morning:

 

On SR 826/Palmetto Expressway ALL northbound lanes will be closed from NW 25 Street to NW 36 Street.

 

Northbound drivers on SR 826/Palmetto Expressway may:

 

  • Take the exit ramp to NW 25 Street
  • Turn east on NW 25 Street
  • Turn north on NW 72 Avenue
  • Turn west on NW 58 Street
  • Take the entrance ramp to SR 826/Palmetto Expressway northbound
  •  

Friday, June 2, from 11 p.m. to Saturday, June 3 at 10 a.m.:

 

On SR 826/Palmetto Expressway northbound, just north of W. Flagler Street, two lanes will be closed on the ramp to SR 826/Dolphin Expressway eastbound.

 

Friday, June 2 from 10 p.m. to 5 a.m. of the following morning:

 

On SR 826/Palmetto Expressway one northbound outside lane will be closed at Okeechobee Road.

 

This schedule may change due to bad weather or unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

The contractor for the Palmetto Express project will be performing roadway work on SR826/Palmetto Expressway including, traffic switch. bridge work, relocating attenuators and  temporary barrier walls, drainage, paving, sign installation, median drilled shaft, road widening, and drainage work on frontage roads.  This schedule may change due to bad weather or other unforeseen conditions. For the latest Palmetto Express project traffic updates, please visit www.palmettoexpresslanes.comand click on the “lane closures” tab

For more information about the Palmetto Express project, please contact Construction Public Information Specialist Marta Rodriguez at 305-592-6026 or go to: www.PalmettoExpressLanes.com.

Drivers are encouraged to call 511 before they drive, or log on to www.fl511.comto get real-time traffic and lane closure information.  The Florida Department of Transportation (FDOT) reminds drivers that wearing a safety belt is the single most effective way to protect people and reduce fatalities in motor vehicles crashes.  Please drive cautiously in work zones.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

05-26-2017
W 20 Ave
Plus sign Construction Wed 05-11-2016 to Sat 09-30-2017

From May 2017 to approximately September 2017, from 10 p.m. to 5 a.m. of the following morning:

 

On West 20 Avenue (West) from NW 122 Street/West 68 Street to West 23 Avenue/NW 138 Street, and on NW 138 Street, there will be flagman operations at various locations. The flagman will be directing traffic during this time. Access to properties will be maintained open.

 

From Thursday, April 20 until approximately the end of May 2017, each day from 9 a.m. to 3:30 p.m.:

 

On West 20 Avenue (East), from West 84 Street/NW 138 Street to NW 76 Street the southbound lane will be closed.  Only local traffic will be allowed on West 20 Avenue (E) during this time.  Access will be provided to businesses.  A flagman will allow local traffic in and out of the businesses during this time.  

 

No parking will be allowed adjacent to the southbound lane along the work zone on West 20 Avenue (E) within the FDOT right-of-way.

 

Eastbound and westbound drivers on West 84 Street/ NW 138 Street heading to West 20 Avenue (E) southbound may:

 

·        Turn south on West 16 Avenue

·         Turn west on West 76 Street

·         Turn south on West 20 Avenue (E)

 

This schedule may change due to bad weather or unforeseen conditions.Interruption of water service is not anticipated.

 

From Monday September 26, 2016 at 6 a.m. and continuing for approximately July 31, 2017:

 

The southbound lane along West 20 Avenue (E), between West 44 Place and West 41 Street, will be completely closed 24 hours around the clock.  Access to businesses will be maintained open at all times via the northbound lane along West 20 Avenue (E).  No parking will be allowed adjacent to the southbound lane along the work zone on West 20 Avenue (E)  within the FDOT right-of-way.

 

Southbound drivers on West 20 Avenue (E)  may:

 

·         Turn east (left) on West 44 Place

·         Turn south (right) on West 18 Avenue

·         Turn west (right) on West 41 Street

·         Turn north (right) on West 20 Avenue (E)

 

Southbound drivers on West 19 Court heading to West 20 Avenue (E) southbound may:

 

·         Turn east (left) on West 44 Place

·         Turn south (right) on West 18 Avenue

·         Turn west (right) on West 41 Street

·         Turn north (right) on West 20 Avenue(E)

 

Drivers on West 18 Avenue heading to West 20 Avenue(E) southbound may:

 

·         Turn west on West 41 Street

·         Turn north on West 20 Avenue (E)

 

Drivers on West 44 Place heading to West 20 (E) southbound may:

 

·         Turn south on West 18 Avenue

·         Turn west on West 41 Street

·         Turn north on West 20 Avenue (E)

 

Please note that schedules may change due to bad weather or other unforeseen conditions.

 

From Wednesday, May 11, 2016 at 6 a.m. and continuing until approximately July 31, 2017:

 

The southbound lane along West 20 Avenue (E), between just south of West 39 Street and West 41 Street, will be completely closed 24 hours around the clock.  Access to businesses will be maintained open at all times via the northbound lane along West 20 Avenue (E).  No parking will be allowed adjacent to the southbound lane along the work zone on West 20 Avenue (E)  within the FDOT right-of-way.

 

Drivers on West 20 Avenue (E) heading southbound may:

 

  • Turn east on West 41 Street
  • Turn south on West 18 Avenue
  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Drivers on West 18 Avenue heading to West 20 Avenue (E) southbound may:

 

  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Drivers on West 41 Street heading to West 20 Avenue (E) southbound may:

 

  • Turn south on west 18 Avenue
  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Please note that schedules may change due to bad weather or other unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

 These closures are necessary to relocate the water main an to widen the Palmetto Expressway as part of the Palmetto Express project by the FDOT District six.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

05-24-2017
NW 77 Ct
Plus sign Construction Wed 05-03-2017 to Thu 08-31-2017

LANE CLOSURES ON NW 77 COURT IN MIAMI-DADE COUNTY AND TOWN OF MEDLEY:

 

From May, 2017 to approximately August, 2017, daytime and nighttime hours

 

On NW 77 Court frontage road (west side of Palmetto Expressway) between NW 58 Street and NW 74 Street, there will be daytime and nighttime flagman operations at various locations. The flagman will be directing traffic and access to businesses will be maintained at all times.

 

This schedule may change due to bad weather or unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

The contractor will be performing road widening work to add express lanes on SR 826/Palmetto Expressway.

 

For more information about the Palmetto Express project, please contact Construction Public Information Specialist Marta Rodriguez at 305-592-6026.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

05-26-2017
NW 77 Ave
Plus sign Construction Mon 02-08-2016 to Mon 07-31-2017

NW 77 Avenue Frontage Road Closures and Detours as Part of the Palmetto Express Project 

 

Starting the week of February 13, 2017 and continuing until approximately July, 2017, 24 hours around the clock:

 

On NW 77 Avenue (west side of SR 826/Palmetto Expressway), from NW 95 Street to NW 98 Street the northbound lane will be closed.  Access to businesses will be maintained open at all times via the southbound lane along NW 77 Avenue.

 

Drivers on North Okeechobee Road and South Okeechobee Road heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

·         Turn north-east onto NW 95 Street

·         Turn north on NW 80 Avenue

·         Turn east on NW 98 Street

·         Turn south only on NW 77 Court

 

Drivers on West Okeechobee Road heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

·         Continue south to NW 95 Street

·         Turn north on NW 80 Avenue

·         Turn east on NW 98 Street

·         Turn south only on NW 77 Court

Drivers at the Walmart store heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

·         Turn west on NW 95 Street

·         Turn north on NW 80 Avenue

·         Turn east on NW 98 Street

·         Turn south only on NW 77 Court.

 

Starting the week of November 21, 2016 and continuing until approximately July 31, 2017, 24 hours around the clock:

 

The southbound lane along NW 77 Avenue (east side of SR 826/Palmetto Expressway) between just south of NW 31 Street and NW 35 Terrace will be completely closed.  Access to businesses will be maintained open at all times via the northbound lane along NW 77 Avenue.

 

Drivers on NW 35 Terrace and on NW 31 Street heading to NW 77 Avenue southbound may:

 

·         Turn south on NW 74 Avenue

·         Turn west on NW 25 Terrace

·         Turn north on NW 75 Avenue

·         Turn west on NW 26 Street

·         Turn north on NW 77 Avenue

 

The southbound lane along NW 77 Avenue (east side of Palmetto Expressway) from NW 43 street to NW 54 Street will be completely closed 24 hours around the clock starting Thursday, May 19, 2016 at 6 a.m. and continuing until approximately July 31, 2017.

 

Access to businesses will be maintained open at all times via the northbound lane along NW 77 Avenue.  

 

No parking will be allowed adjacent to the southbound lane along the work zone on NW 77 Avenue within the FDOT right-of-way.

 

Drivers on NW 54 Street heading to NW 77 Avenue southbound may:

 

  • Turn south on NW 74 Avenue
  • Turn east on NW 44 Street
  • Turn south on NW 73 Avenue
  • Turn west on NW 43 Street
  • Turn north on NW 77 Avenue

 

Drivers on NW 74 Avenue heading to NW 77 Avenue southbound may:

 

  • Turn east on NW 44 Street
  • Turn south on NW 73 Avenue
  • Turn west on NW 43 Street
  • Turn north on NW 77 Avenue

 

 

 

This schedule may change due to bad weather or other unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

As part of the Palmetto Express project by the Florida Department of Transportation, District Six, the contractor will start widening the Palmetto Expressway and performing drainage improvements along NW 77 Avenue, on the west side and east side of the Palmetto Expressway in the City of Hialeah Gardens.

 

For more information about the Palmetto Express project, please contact Construction Public Information Specialist Marta Rodriguez at 305-592-6026. 

 

Please drive cautiously in work zones.  THANK YOU.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

05-19-2017


Contact

Florida Department of Transportation

Toll Free- 1-866-513-7623

Express Lanes / FDOT logo
lines

Marta Rodriguez, Public Information Specialist

Phone: (305) 592-6026|E-mail: Marta.Rodriguez@dot.state.fl.us

Kathy McLendon, Construction Public Information Project Manager

Phone: (305) 640-7437|E-mail: Kathy.McLendon@dot.state.fl.us

Tish Burgher, District Public Information Officer

Phone: (305) 470-5349|E-mail: Tish.Burgher@dot.state.fl.us