Lane Closures

     For information on other FDOT lane closures and projects, click here.

PRINT

SR 826/Palmetto Expwy
Plus sign Construction Mon 11-20-2017 to Tue 11-21-2017

NIGHTTIME/DAYTIME LANE CLOSURES ON SR 826/PALMETTO EXPRESSWAY AND I-75:

 

The Palmetto Express Lanes project will not have any closures due to the Thanksgiving Holiday, from Wednesday, November 22 through Sunday, Novemeber 26.

Projects:

1SR 826/Palmetto Express Lanes

Details:

The contractor for the Palmetto Express project will be performing roadway work on SR826/Palmetto Expressway including, installation of temporary barrier wall and wall demolition, bridge work, directional boring, miling and paving median drill shaft, drainage, paving,  widenning, and drainage work on frontage roads.  This schedule may change due to bad weather or other unforeseen conditions. For the latest Palmetto Express project traffic updates, please visit www.palmettoexpresslanes.com and click on the “lane closures” tab, or call the Public Information Specialist Marta Rodriguez at 305-592-6026.

For information about the Florida Express Lanes Network, please visit www.floridaexpresslanes.com

Drivers are encouraged to call 511 before they drive, or log on to www.fl511.comto get real-time traffic and lane closure information.  The Florida Department of Transportation (FDOT) reminds drivers that wearing a safety belt is the single most effective way to protect people and reduce fatalities in motor vehicles crashes.  Please drive cautiously in work zones.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

11-22-2017
W 20 Ave
Plus sign Construction Wed 05-11-2016 to Sun 12-31-2017

From Wednesday, May 11, 2016 at 6 a.m. and continuing until approximately December 31, 2017:

 

The southbound lane along West 20 Avenue (E), between just south of West 39 Street and West 41 Street, will be completely closed 24 hours around the clock.  Access to businesses will be maintained open at all times via the northbound lane along West 20 Avenue (E).  No parking will be allowed adjacent to the southbound lane along the work zone on West 20 Avenue (E)  within the FDOT right-of-way.

 

Drivers on West 20 Avenue (E) heading southbound may:

 

  • Turn east on West 41 Street
  • Turn south on West 18 Avenue
  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Drivers on West 18 Avenue heading to West 20 Avenue (E) southbound may:

 

  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Drivers on West 41 Street heading to West 20 Avenue (E) southbound may:

 

  • Turn south on west 18 Avenue
  • Turn west on West 35 Street
  • Turn north on West 20 Avenue (E)

 

Please note that schedules may change due to bad weather or other unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

 These closures are necessary to relocate the water main an to widen the Palmetto Expressway as part of the Palmetto Express project by the FDOT District six.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

11-13-2017
NW 77 Ave
Plus sign Construction Mon 02-08-2016 to Tue 10-31-2017

NW 77 Avenue Frontage Road Closures and Detours as Part of the Palmetto Express Project 

Thursday May 19, 2016 to December 31, 2017:

The southbound lane along NW 77 Avenue (east side of Palmetto Expressway) from NW 43 street to NW 54 Street will be completely closed 24 hours around the clock starting Thursday, May 19, 2016 at 6 a.m. and continuing until approximately December 31, 2017.

 

Access to businesses will be maintained open at all times via the northbound lane along NW 77 Avenue.  

 

No parking will be allowed adjacent to the southbound lane along the work zone on NW 77 Avenue within the FDOT right-of-way.

 

Drivers on NW 54 Street heading to NW 77 Avenue southbound may:

 

  • Turn south on NW 74 Avenue
  • Turn east on NW 44 Street
  • Turn south on NW 73 Avenue
  • Turn west on NW 43 Street
  • Turn north on NW 77 Avenue

 

Drivers on NW 74 Avenue heading to NW 77 Avenue southbound may:

 

  • Turn east on NW 44 Street
  • Turn south on NW 73 Avenue
  • Turn west on NW 43 Street
  • Turn north on NW 77 Avenue

 

Starting the week of February 13, 2017 and continuing until approximately December, 2017, 24 hours around the clock:

 

On NW 77 Avenue (west side of SR 826/Palmetto Expressway), from NW 95 Street to NW 98 Street the northbound lane will be closed.  Access to businesses will be maintained open at all times via the southbound lane along NW 77 Avenue.

 

Drivers on North Okeechobee Road and South Okeechobee Road heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

  • Turn north-east onto NW 95 Street
  • Turn north on NW 80Avenue
  • Turn east on NW 98 Street
  • Turn south only on NW 77 Court

 

Drivers on West Okeechobee Road heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

  • Continue south to NW 95 Street
  • Turn north on NW 80Avenue
  • Turn east on NW 98 Street
  • Turn south only on NW 77 Court

 

Drivers at the Walmart store heading to NW 77 Court northbound to access businesses between NW 95 Street and NW 98 Street may:

 

  • Turn west on NW 95 Street
  • Turn north on NW 80 Avenue
  • Turn east on NW 98 Street
  • Turn south only on NW 77 Court.

 

From Monday, February 8, 2016 and continuing until approximately December 31, 2017, 24 hours around the clock:

 

The southbound lane along NW 77 Avenue (east side of SR 826/Palmetto Expressway) between NW 70 Street and NW 66 Street will be completely closed.  Access to businesses will be maintained open at all times via the northbound lane along NW 77 Avenue.

 

Drivers heading south on NW 77 Avenue can:

 

  • Turn east on NW 70 Street
  • Turn south on NW 74 Avenue
  • Turn west on NW 66 Street
  • Turn south on NW 77 Avenue

 

Drivers on NW 70 Street westbound heading to NW 77 Avenue southbound can:

 

  • Turn south on NW 74 Avenue
  • Turn west on NW 66 Street
  • Turn south on NW 77 Avenue

 

Drivers on NW 74 Avenue heading to NW 77 Avenue southbound can:

 

  • Turn west on NW 66 Street
  • Turn south on NW 77 Avenue

 

This schedule may change due to bad weather or other unforeseen conditions.

Projects:

1SR 826/Palmetto Express Lanes

Details:

As part of the Palmetto Express project by the Florida Department of Transportation, District Six, the contractor will start widening the Palmetto Expressway and performing drainage improvements along NW 77 Avenue, on the west side and east side of the Palmetto Expressway in the City of Hialeah Gardens.

 

For more information about the Palmetto Express project, please contact Construction Public Information Specialist Marta Rodriguez at 305-592-6026. 

 

Please drive cautiously in work zones.  THANK YOU.

Contact Info:

Marta Rodriguez
305-592-6026

Last Updated On:

11-13-2017


Contact

Florida Department of Transportation

Toll Free- 1-866-513-7623

Express Lanes / FDOT logo
lines

Marta Rodriguez, Community Outreach Specialist

Phone: (305) 592-6026|E-mail: Marta.Rodriguez@dot.state.fl.us

Kathy McLendon, District Construction Public Information Project Manager

Phone: (305) 640-7437|E-mail: Kathy.McLendon@dot.state.fl.us

Tish Burgher, District Communications Manager

Phone: (305) 470-5349|E-mail: Tish.Burgher@dot.state.fl.us